Skip to content

Validate technology · Scale production

Good technologies rarely fail in the lab. They fail at the step into the plant.

Your pilot is running. Your investor asks about the first industrial plant, or the new hall has to produce. What is missing is the engineer who sees process, plant and manufacturing at the same time. I am Tobias Breitbach, and I close exactly that gap.

How would you like to start?

I will send you a short, personal email. No newsletter.

I call you back personally, usually the same working day.

15 minutes to get to know each other, no obligation. You get a confirmation by email.

I only use your details for this request. Privacy policy

Smaller first packages often start the next day

The problem

Do you recognise one of these sentences from your last meeting?

The expensive mistakes do not happen in research. They happen at the transitions, where decisions suddenly cost a lot of money and are hard to reverse.

Scale-ups

“The EPC wants basic data we do not have yet.”

The requirements specification has gaps, and the interfaces to the Balance of Plant are open.

  • Gaps in the specification
  • Change orders from the plant builder
  • First plant delayed
  • Investor milestone missed
Pilot → first plant (DE)
Scale-ups

“Demand is there, but our stack is still handmade.”

The design is not ready for series, and assembly and testing do not scale with it.

  • Manual assembly
  • Scrap during ramp-up
  • Late deliveries against the order book
Stack → series (DE)
Production

“The new hall is nearly built. But who plans how we produce in it?”

The building grid is fixed before the process layout is. The production planner does it “on the side”.

  • Layout follows the building line, not the process
  • Detours and interim storage
  • Lead time rises
  • Delivery reliability falls
Hall & material flow (DE)

+33 %cost and +30 % time on large projects with weak front-end planning.Source: IPA/Merrow 2012, industrial megaprojects > USD 1 bn

73 %of variant manufacturers miss their delivery-reliability target, by 21 percentage points on average.Source: Fraunhofer IPA, n = 500

≈ 99,470open engineering positions in Germany. Senior capacity is missing exactly when time is short.Source: VDI/IW Ingenieurmonitor Q3/2025

The real problem

Technology is rarely what is missing. What is missing is someone who owns the transitions.

Between lab, plant and production lie interfaces that nobody feels responsible for. That is exactly where the expensive mistakes happen.

01 · Your team

Fully occupied with the core technology.

Cell chemistry, software, customers: there is no time left for the specification, balance of plant and production. These tasks get done "on the side".

02 · The plant builder

Builds what the specification says, not what you mean.

Every gap in the basic data later becomes a change order. If you do not staff your side of the table, you pay twice.

03 · The interfaces

Process, plant and production are planned separately.

Everyone optimises their own part. Whether the whole works only shows at commissioning, when changes are most expensive.

3–5 %of the investment is what thorough front-end planning costs, a fraction of what change orders and delays cost later.Source: IPA/Merrow 2012, rule of thumb for large projects

The answer is not a large consulting team. It is one experienced engineer on your side who checks the critical 10 %: the interfaces between process, plant and production.

Where the risk arises

Good technologies often fail at scale-up.

Much works up to the lab. The decisive risks arise at the transitions to the prototype and test rig, to the pilot plant and into series production.

  1. IdeaTest assumptions on product properties and production cost early.
  2. LabSecure the main function before the prototype is built and expensive steps follow.
  3. Prototype / test rigMake sure the prototype works and the relevant risks measurably fall.Critical transition
  4. Pilot plantBring edge cases and possible disturbances to light in trial operation.Critical transition
  5. Series productionSecure quality and target cost at high volumes as well.Critical transition

I start where technical decisions become expensive and hard to reverse.

Calculator

What does one month of delay cost you?

With your own figures, in 20 seconds. Nothing is stored or sent.

Example values: replace them with your own. According to the BDI, permitting procedures under the German Federal Immission Control Act (BImSchG) take on average about 6 months longer than the statutory deadline.

Every month of delay costs you250,000 €

The assumed delay costs you in total1,500,000 €

Thorough front-end planning typically costs–3–5 % of the investment · Source: IPA/Merrow 2012, rule of thumb for large projects

Delay as a percentage of your investment: –

How we work together

What happens when you get in touch? Five steps, no surprises.

At every step you know what you do, what you get and how long it takes.

  1. Today · 10 sec.

    Get in touch

    You choose how active to be: information by email, a call back or a short call.

    You do
    Enter your email address or phone number.
    You get
    A personal reply from me: no sales pitch, no newsletter.
    Duration
    10 seconds. Reply usually the same working day.
  2. 15 minutes

    Getting to know each other

    You describe your situation, your goal and your time pressure. I ask the questions your bottleneck raises.

    You do
    Tell me where it gets stuck. No documents needed yet.
    You get
    An honest first assessment, including a no if I am not the right person.
    Duration
    15 minutes, non-binding, by phone or video.
  3. 1–2 hrs · NDA

    First meeting & diagnosis

    Confidentiality first: we sign an NDA. Then we look at data, plans and, where needed, the plant or hall together.

    You do
    Provide data, drawings or access.
    You get
    A clear answer: where the bottleneck is, what it costs and which levers exist, in priority order.
    Duration
    A few days to a few weeks, depending on scope.
  4. Fixed price

    Joint approach

    We agree the goal, scope, milestones and contact persons. We start with a clearly defined package at a fixed price agreed in advance.

    You do
    Decide, on a reliable basis.
    You get
    A project plan that your team, your plant builder and your investors can build on.
    Duration
    Smaller first packages often start the next day.
  5. 6 · 9 months · long term

    Working together on the project

    Depending on the project, I support you for six months, nine months or long term: remotely over the project term, on site when it counts.

    You do
    Work with me as the engineer on your side.
    You get
    Regular alignment, documented decisions and support through to commissioning or start of series production.
    Duration
    6 months, 9 months or long term.

Example

How it works: a typical case.

A scale-up is about to award the contract to the plant builder. Time is short, and the team is busy with cell chemistry. Instead of a large mandate, we start with a design review at a fixed price agreed in advance.

Design review before EPC awardExample, anonymised
  1. Day 1

    Call-back requested. A 15-minute call the same day.

  2. Day 2

    First meeting: NDA signed, documents received.

  3. Weeks 1–2

    Diagnosis: basic data, interfaces and balance of plant reviewed, site visit.

  4. Week 3

    Joint approach: prioritised points before the award, fixed-price package starts.

  5. 6–9 months

    Support through to the award and through the planning of the first plant.

Dr.-Ing. Tobias Breitbach, founder of REAC Energy Dr.-Ing. · Mechanical engineering

About me

Development needs competent grounding.

I keep questioning until it is clear what does not work, or it is out.
  • Mechanical engineering degree, doctorate in production engineering
  • Industrialisation and production systems, from test rig to plant
  • Experience from industry, research and start-ups
  • International projects, including commissioning in the USA
  • Years of hands-on trade experience: I know what the shop floor looks like

REAC Energy is my engineering office. You work directly with me, and with my team where a project needs more hands. I typically run three projects in parallel: few on purpose, so each gets my full attention.

What I do not do

Explosion-protection assessments (ATEX) belong to specialist experts. I bring them in instead of pretending it is mine. And I do not replace an EPC or a large detail-engineering team.

What I do: review the critical interfaces between process, plant and manufacturing so that your EPC and your experts can work cleanly.

References

Electrolysis, hydrogen, factory planning, agritech.

From a design review before EPC award at a climate-tech scale-up with its own electrolysis process to multi-year support of a plant expansion for a German technology group in the USA. Anonymised until the client agrees to be named.

Common questions

Before you ask.

Do you actually have capacity?

My projects are planned so that short-notice assignments remain possible.

What does a first package cost?

Every first package is clearly defined and has a fixed price agreed in advance. You know the cost before you start. There is no open-ended hours budget.

What happens to our data and our IP?

We sign an NDA before any data is exchanged. Your intellectual property stays with you – we set this out in the NDA and the contract.

Why not just hire a freelancer through a platform?

With me you do not get a profile to vet. You get a defined package with a clearly defined deliverable and a fixed price agreed in advance. Clearly separated work packages also make the contract cleaner.

Do you also work abroad?

Yes. For example on a plant expansion in the USA: remotely over the whole term, and on site for the decisive commissioning steps and acceptance tests at the manufacturer.

Language

Detailed topic pages are in German.

REAC Energy is a Germany-focused consultancy, so the detailed topic pages are written in German. The pages marked (DE) open in German. For anything else, write to me in English.

Let us get started

Are you developing, scaling or protecting an investment?

For a smaller, clearly defined first package I can often start the next day: read in, think through, prepare the site visit. From the start you talk to the engineer who also does the work.

How would you like to start?

I will send you a short, personal email. No newsletter.

I call you back personally, usually the same working day.

15 minutes to get to know each other, no obligation. You get a confirmation by email.

I only use your details for this request. Privacy policy

Hydrogen production plants
Hydrogen production plants
Electrolyser series readiness
Electrolyser series readiness
Process industry
Process industry
Climate tech
Climate tech
Factory planning
Factory planning
Agritech
Agritech
Mass production
Mass production
Technical due diligence
Technical due diligence
Dr.-Ing. Tobias Breitbach
Managing Director, REAC Energy GmbH

How would you like to start?

One field is enough. You talk directly to the engineer who also does the work.

How would you like to start?

I will send you a short, personal email. No newsletter.

I call you back personally, usually the same working day.

15 minutes to get to know each other, no obligation. You get a confirmation by email.

I only use your details for this request. Privacy policy

Call-backBy email